Work has started on this two storey side extension in Halfway, Sheffield.
15/03/10
The stonework is now up to roof level, the roof trusses have been ordered and the original outer gable has been demolished to form the new internal layout.
26/03/10
The roof trusses are now on and the gable has been built up. The roof will be covered next week and windows and doors are on order. The client has decided to have the existing fascias, soffits and gutters renewed with UPVC so they will match the new extension.
19/04/10
The roof is now on and the windows are due to be fitted this week, with the plastering and scaffold removal also planned.
Here is the finished extension.